In-House Concrete Slab Work

Completed Slab Replacements
The Sunset Hills Street Department will be replacing selected sidewalk sections on starting May 18, 2015:
  • Tioga Ct - Completed 7/15/15
  • Sandian Ct. - Completed 7/24/15
  • Denny Rd. - Completed 7/31/15
  • Werkdale Dr. - Completed 7/31/15
  • Gates Manor Dr. - Completed 8/7/15
  • Dennison Grove Ct. - Completed 7/31/15
  • 10048 Hilltop Dr. - Completed 8/25/15
  • Fairlind Dr. - Completed 8/25/15
  • Sunlind Dr. - Completed 9/2/15
  • Parklind Dr. - Completed 9/25/15
There will be no street slab replacement done this year by our Street Department:

Scroll to the bottom of the page for the latest information
  • 5/22/15, Street department remove a concrete slab at 10200 Richview Drive.
  • 5/27/15, Street department remove and pumped out the water then removed the mud at 10200 Richview Drive.
  • 5/28/15, Street department prep the slab to pour at 10200 Richview Drive.
  • 5/29/15, Street department broke and remove selective sidewalk squares on Tioga Court.
  • 6/1/15, Street department will be pouring concrete street slab at 10200 Richview Drive. Also working on sidewalk replacements on Tioga Court.  
  • 6/2/15, Street department will be removing selective sidewalks squares on Tioga Court.
  • 6/3/15, Street department will be removing selective sidewalks squares and grinding tree roots on Tioga Court.
  • 6/4/15, Street department will be removing selective sidewalks squares and grinding tree roots on Tioga Court. 
  • 6/5/15, Rain day. No one onsite.
  • 6/8/15, Rain day. No one onsite.
  • 6/9/15, Street department will be removing and preparing sidewalks to pour at 12574 Glencroft. 
  • 6/10/15, Street department prepare sidewalks to pout on Glencroft Drive. Bale water, set forms and placed rock on Tioga Court. 
  • 6/11/15, Street department formed, rock and poured sidewalks on Tioga Court. 
  • 6/12/15, Street department prepared open holes to replace sidewalks on Tioga Court.
  • 6/15/15, Street department prepared open holes to replace sidewalks on Tioga Ct.
  • 6/16/15, Rain day.
  • 6/17/15, Rain day.
  • 6/18/15, Rain day.
  • 6/19/15, Rain day.
  • 6/22/15, Street department pumped out holes and form open sidewalk areas on Tioga Court.
  • 6/23/15, Street department pumped out holes and placed rock in open sidewalk areas on Tioga Court.
  • 6/24/15, Street department will be pouring 5 yards of concrete at 1:00pm for sidewalks on Tioga Court.
  • 6/25/15, Street department will be pouring 5 yards of concrete at 9am. They will also start preparing additional sidewalks to pour on Tioga Court.
  • 6/26/15, Rain day.
  • 6/29/15, Street department will be pumping water, setting forms and placing rock in open holes for sidewalk replacements on Tioga Court.
  • 7/1/15, Rain day. After lunch Street department prepared areas of sidewalk to pour tomorrow, on Tioga Court.
  • 7/2/15, Rain day.
  • 7/3/15 , Holiday.
  • 7/6/15, Tioga Court, Street department will back fill behind new sidewalks that have been poured.   
  • 7/7/15, Rain day.
  • 7/8/15, Rain day.
  • 7/9/15, Street department will be back filling behind new sidewalk that have been poured. Also remove water from open holes to pour tomorrow pending rain on Tioga Court.
  • 7/10/15, Rain day. Started raining over night, Street Department will pump out the water in the open holes when the rain stops today. Hopeful to pour on Monday, on Tioga Court.
  • 7/1315, Poured concrete sidewalks at 9:00am, Removed wash out pile and cleaned Tioga Court. Also broke sidewalks on Sandian Court.
  • 7/14/15, Remove forms from concrete poured yesterday for sidewalks replacements, then backfill, seed and fertilize on Tioga Court, Also dig out and form for selective sidewalk replacements on Sandian Court. 
  • 7/15/15, Finish backfill, seed, fertilizing and place matting behind new concrete sidewalks on Tioga Court. Remove and form selective sidewalks on Sandian Court.
  • 7/16/15, Street department will remove and form selective sidewalks on Sandian Court. Street Superintendent & Street Foreman inspected and marked the streets that are at the top of this page to replace selective sidewalks.
  • 7/17/15, Street department will remove and form selective sidewalks on Sandian Court.
  • 7/20/15, Street department will remove and form selective sidewalks on Sandian Court. Street department pulled off site due to the rain @ 9:40am today. 12:30pm, rain has stopped, Street Department is back on Sandian Court preparing sidewalks to pour tomorrow. Pending weather. 
  • 7/21/15, Street department will be preparing open areas to pour concrete for sidewalk replacements. Also pour concrete at 12:30pm today on Sandian Court. 
  • 7/22/15, 12:30pm today, Street department will be be setting forms and placing rock in open areas for selective sidewalk replacements on Sandian Court. 
  • 7/23/15, 9:30am, pour concrete in open holes for selective sidewalk replacements. Remove forms, backfill, fertilize, seed areas behind concrete sidewalks poured on Sandian Court, July, 21, 2015.
  • 7/24/15, Street department will be removing forms, backfill, seed, fertlize behind new sidewalks that were poured yesterday, also clean roadway on Sandian Ct. Saw cut and break sidewalks for replacement with ADA ramps at the intersections streets of Denny Road. 
  • 7/27/15, Street department will remove and form sidewalks for replacement with ADA ramps at the intersecting streets of Denny  Road.
  • 7/28/15, Street department will remove and form sidewalks for replacement with ADA ramps at the intersecting streets of Denny Road.  
  • 7/29/15, Street department will be pouring concrete at 8:00am. Then prepare additional sidewalks to pour on Denny Road.
  • 7/30/15, Street department will be pouring concrete at 7:30am & 10:00am for ADA ramps on Denny Road. Also break and removing selective sidewalks on Gates Manor Ct.
  • 7/31/15, Street department will be removing forms and back filling, seeding, fertilize and place matting material as needed. Also remove Traffic Control from Denny Road. Start removing and forming selective sidewalk on Gates Manor.
  • 8/3/15, Street department will be removing selective sidewalks and placing forms on Gates Manor Court. An additional crew will be marking selective sidewalks to replace on Sunlind Drive & Parklind Drive.
  • 8/4/15, Street department will be removing and preparing additional selective sidewalks to pour on Gates Manor Court. 
  • 8/5/15, Rain day. Rain stopped at 10am this morning, Street department will be preparing selective sidewalks to pour at a later date on Gates Manor Court.
  • 8/6/15, Street department has two concrete deliveries today at 9:00am & 10:30am on Gates Manor Court. Also remove and prepare a sidewalk section for pour at a later date. 
  • 8/7/15, Street department will remove forms from concrete sidewalks poured yesterday, back fill, seed, fertilize and place matting. Also remove all traffic control from Gates Manor Court.
  • 8/14/15, Street department will remove and prepare selective sidewalks to replace at 10048 Hilltop Drive.
  • 8/17/15, Street department will pour concrete for open sidewalk at 9:30am today at 10048 Hilltop Dr. Also start breaking and removing selective sidewalks on Fairlind Dr. 
  • 8/18/15, Street department will removing and placing forms on selective sidewalks at Fairlind Drive.
  • 8/19/15, Rain day. Rained very hard last night. Rain is forcasted for this afternoon.
  • 8/20/15, Street department will prepare sidewalks to pour tomorrow on Fairlind Dr.
  • 8/21/15, Street department will be pouring concrete sidewalks @ 8:00am & 10:30am on Fairlind Drive. 
  • 8/24/15, Street department will removing forms, backfill, seed, fertilize and place matting material as needed, behind sidewalks poured yesterday and removed rock wash out pile on Fairlind Drive.
  • 8/25/15, Street department will backfill, seed, fertilize and place matting material as need on Fairlind Drive. Back fill and sod behind the new sidewalk poured, on Hilltop Drive. 
  • 8/26/15, Street department will be checking behind all new sidewalks poured this year for low areas and add topsoil, seed, fertilize as needed. Also break and remove selective sidewalks on Sunlind Drive. 
  • 8/27/15, Street department will prepare and pour concrete at 11:00am, for selective sidewalks on Sunlind Drive.
  • 8/28/15, Street department will prepare and pour concrete at 9am, for selective sidewalks on Sunlind Drive.
  • 8/31/15, Street department will remove forms, back fill, seed, fertilize, seed and place matting material for sidewalks poured last Friday on Sunlind Drive.
  • 9/1/15, Street department will pour concrete at 9am on Sunlind Drive for the open sidewalk. Also dig out and place forms for selective sidewalks on Parklind Drive.
  • 9/2/15, Street department will remove the forms from concrete sidewalks poured yesterday on Sunlind Drive. Also dig out and form selective sidewalks on Parklind Drive.
  • 9/3/15, Street department prepare selective sidewalks to pour tomorrow on Parklind Drive.
  • 9/4/15, Street department prepare selective sidewalks to pour and has a pour today at 10:15am on Parklind Drive. 
  • 9/8/15, Street department will be removing forms from sidewalks poured last Friday. Also prepare selective sidewalks to pour at a later date on Parklind Drive. 
  • 9/10/15, Street department will remove water from open holes on Parklind Drive.
  • 9/11/15, Rain day.
  • 9/14/15, Street department will pour concrete at 8am, then prepare additional selective sidewalks to pour tomorrow on Parklind Drive.
  • 9/15/15, Street department will pour concrete, then prepare additional selective sidewalks on Parklind Drive.  
  • 9/17/15, Street Department will pour Concrete at 8am, then remove forms and back fill, seed, fertilize behind concrete poured on Tuesday for Parklind drive.
  • 9/18/15, Street department will be back filling, seeding, fertilizing, behind new sidewalks on Parklind Drive. 
  • 9/21/15, Street department is waiting on Ameren Missouri Electic to repair their line on Parklind so we can finish this project.  
  • 9/22/15, Street department will be pouring concrete at 11:00am on the (2) last ADA ramps today on Parklind Drive.
  • 9/25/15, Street department will remove concrete forms back fill, seed and fertilize behind new sidewalks poured last Tuesday on Parklind Drive. This will complete our sidewalk replacement for 2015.