In-House Concrete Work

Street Slab Replacement

  • Windsor springs
  • Royal springs
  • Rygate
Sidewalk Sections
  • Eddie & Park
  • Old Gravois (by Mini Ha-ha)
  • East Watson
Update
  •  - The Sunset Hills Street Department will be performing selected street slab and sidewalk section replacement in the City in 2021.  Look here for updates or contact Street Foreman Jason Miller at jmiller@sunset-hills.com for details.
Ryegate
  • 6/15/21 - Removal of asphalt apron 
  • 6/17/21 - Concrete forms installed
  • 6/18/21 -  Concrete to be placed on outgoing lane (canceled due to 100 degree plus temperatures)
  • 6/21/21 -  Water pumped from hole from weekend storms rock added to firm up base
  • 6/23/21 - Concrete approach poured  outgoing lane
  • 6/24/21 - Concrete forms removed, control joints cut, curb formed
  • 6/28/21- Open outgoing lane to traffic, remove rock from incoming lane install concrete form(rained out after lunch)
  • 6/29/21- Pump water from hole from yesterdays storms, add rock to base and grade
  • 6/30/21 Install rebar, pump water from hole
  • 7/1/21  8 am concrete pour rained out, Pump water from hole
  • 7/2/21 11am concrete pour incoming lane , lane will be open to traffic 7/6/21
Forrest Circle
  • 7/12/21 -  Removal of concrete slabs begin
  • 7/13/21 - Grade rock and install concrete forms
  • 7/15/21 - concrete replaced will be open to traffic 7/21/21
  • 7/16/21 - saw cut control, joints repair sprinklers
  • 7/19/21 - concrete forms removed, backfill begun
  • 7/20/21 - Saw cut, break and remove concrete street slabs
  • 7/21/21 - Remove street slabs
  • 7/22/21 - Form, grade rock install rebar
  • 7/26/21 - pour back concrete street slabs 8am  (weather pending) street will fully reopen 7/30/21
Windsor springs/ Royal springs
  • 9/10/21- saw cut of selected slabs to be removed
  • 9/13/21- Removal and grading of concrete slabs to be replaced
  • 9/14/21 - Removal and grading of concrete slabs to be replaced
  • 9/15/21 - Removal and grading of concrete slabs to be replaced
  • 9/16/21 - Concrete to be poured 8am intersection of  Royal springs/ Windsor springs  and Royal springs /Wicksworth
  • 9/20-9/21/21  - Removal of concrete street slabs to be replaced
  • 9/22/21 - Concrete pour 8am, newly poured street slabs will be open to traffic 9/27/21
  • 9/23/21  - Saw cutting of expansion joints on newly poured street slabs
  • 9/27 - 9/28/21 - Removal of street slabs to be replaced
  • 9/29/21 - Grading of rock and rebar installed
  • 9/30/21 - Concrete pour 8am , (Weather pending) Newly poured street slabs will be open for traffic on 10/4/21
  • 10/4/21 - concrete poured 14 yards  this section will be open to traffic on 10/8/21
  • 10/5/21 -  expansion joints saw cut
  • 10/6/21 - saw cutting, breaking and removal of concrete street slab to be replaced in eyebrow at1454 Royal springs
  • 10/12/21 - concrete street slab poured  today
  • 10/13/21 - sweeping and clean up of streets was completed . street will be fully opened on 12/15/21
  • concrete street slab replacement is complete in this area